Mass.gov  
Massachusetts Bay Transportation Authority (MBTA) Massachusetts Department of Transportation
Green Line Extension Green Line Extension
Contract Status
  

 

The GLX "Phase 1" construction contract (E22CN01) is complete. Work included the reconstruction of the Harvard Street Railroad Bridge in Medford and the Medford Street Railroad Bridge in Somerville as well as the demolition of the MBTA-owned facilities at 21 Water Street in Cambridge.

The Interim Guaranteed Maximum Price (IGMP) construction contracts (E22CN02, E22CN03, E22CN04, and E22CN06) are in the close-out phases. Work included the procurement of long lead items, utility relocations, drainage improvements, and track infrastructure.

The MBTA has retained a Design Professional (DP) in accordance with the requirements of Massachusetts General Law Chapter 149A, Section 18. The DP is responsible for the overall management of all technical and design aspects of the Design Build procurement, design, and construction phases of the GLX program.

The procurement process for the GLX Design Build contract is well underway, and all milestones to date have been met. The MBTA has selected a short-list of three teams, and final Design Build proposals are scheduled for submission on September 28, 2017. The Design Build Notice to Proceed is now scheduled to occur on December 11, 2017, two months earlier than previously planned. The Design Build entity will perform both the final design services and all remaining GLX construction scope.

The MBTA is currently in the final stages of the procurement process for contracting with a Program Management/Construction Management (PM/CM) firm.